How this volume estimate works
This planning calculation assumes one day of sewage plus stored sludge. Its flow rates, 25% margin and 1,800 litre floor are calculator assumptions, not a reproduction of the IS 2470 sizing tables:
| Part | Formula | Typical value |
|---|---|---|
| Daily flow | people × litres per person | 90 L (toilet only) or 130 L (with bath and kitchen) |
| Sludge | people × 30 L × years between cleanings | 30 L per person per year |
| Allowance | (flow + sludge) × 1.25 | At least 1,800 L in total |
The suggested size keeps the length about 2.2 times the width, with a liquid depth between 1.0 and 1.5 m that grows with the number of users. A baffle wall splits the length 2 : 1 into the two chambers. The editable air-space allowance is separate from liquid capacity.
Worked example: a family of 6
- Toilet waste only: 6 × 90 = 540.00 litres a day.
- Sludge over 2 years: 6 × 30 × 2 = 360.00 litres.
- With the 25% allowance: 1,125.00 litres, below the minimum, so the tank holds 1,800.00 litres.
- At a liquid depth of 1.02 m and length 2.2 × width, that is 6' 6" (1.97 m) long and 2' 11" (0.90 m) wide.
- Chamber 1 is 4' 4" long and chamber 2 is 2' 2".
Checks before construction
Why two chambers
In a single chamber, the incoming flow stirs up solids and pushes them straight to the outlet, which clogs the soak pit. The first chamber holds about two thirds of the volume and traps most of the solids; the second receives partially settled effluent. The inlet, outlet and baffle geometry need a separate design.
Site and disposal checks
Confirm local-authority setbacks from wells, foundations and boundaries. A fixed distance cannot establish safety for every soil or groundwater condition. Effluent still contains pathogens and needs an approved disposal or treatment arrangement.
Soakage area and depth depend on tested infiltration, daily flow, seasonal groundwater and rock. Do not size a soak pit from household count alone. The example dimensions are not a construction recommendation.
References: IS 2470 (Part 1):1985 and (Part 2):1985, listed in the BIS CED 24 programme checked on 6 November 2026. Apply the amendments and local approval requirements with your engineer.