How the quantities are worked out
- Wet volume of the member: length × width × thickness (or the column, beam or footing size), times the number of pieces.
- Add wastage, usually 5%.
- Multiply by the dry volume factor, 1.54, to allow for the voids that close up when water is added.
- Split the dry volume by the mix ratio. For the M20 reference ratio (1 : 1.5 : 3), cement is 1 part in 5.5.
- Cement: m³ × 1,440 kg ÷ 50 kg per bag, rounded up to whole bags. Sand weighs about 1,600 kg per m³ and aggregate about 1,550 kg.
- Water: 25 litres per bag, a water-cement ratio of 0.5.
| Reference | Cement : sand : aggregate | Scope |
|---|---|---|
| 1 : 1 : 2 preset | 1 : 1 : 2 | Quantity estimate only; not an M25 design mix |
| M20 reference | 1 : 1.5 : 3 | M20 reference estimate; confirm the approved mix |
| M15 reference | 1 : 2 : 4 | Plain concrete, paths, kerbs |
| M10 reference | 1 : 3 : 6 | Levelling course under foundations |
| M7.5 reference | 1 : 4 : 8 | Lean concrete under footings |
Worked example: 10 m³ of M20
- Dry volume: 10 × 1.54 = 15.4 m³. The mix has 1 + 1.5 + 3 = 5.5 parts.
- Cement: 15.4 ÷ 5.5 = 2.8 m³ × 1,440 kg = 4,032 kg, which is 80.6, so 81 bags (8.06 bags per m³).
- Sand: 15.4 × 1.5 ÷ 5.5 = 4.2 m³, about 148 cft or 6.7 tonnes.
- Aggregate: 15.4 × 3 ÷ 5.5 = 8.4 m³, about 297 cft or 13 tonnes.
- Water: 80.6 bags × 25 litres = about 2,016 litres.
Getting good concrete on site
IS 456 prefers design mixes. Nominal mixes are limited to M20 or lower and need the engineer-in-charge's permission when a design mix cannot be used. The 1 : 1 : 2 preset here estimates quantities only; it does not establish M25 strength. See the government audit discussion of IS 456, section 7.10.3.
Reviewed 6 November 2026. Dry volume factors, loose densities, water and prices are estimating assumptions; use the approved mix and measured site conditions.
- Batch by volume carefully. Use a gauge box for sand and aggregate rather than counting head pans; small errors add up over a slab.
- Do not add extra water to make pouring easier. Each extra litre lowers the strength. Use a plasticiser if the mix is too stiff.
- Compact well. Use a needle vibrator so no air pockets are left around the steel.
- Cure for at least 7 days (10 to 14 for PPC cement) by ponding or wet hessian.