How it is calculated
- Net surface area = gross area - openings, converted to m². Each face must be counted explicitly.
- Wet plaster volume = net area × total thickness in mm ÷ 1,000. Dry ordering volume = wet volume × dry factor × (1 + allowance ÷ 100).
- For 1:s sand parts, cement mass = dry ordering volume ÷ (1 + s) × loose cement density. Bags = cement mass ÷ 50, rounded up. Sand = dry ordering volume × s ÷ (1 + s).
- Cost = full cement bags × price per bag + unrounded sand volume in m³ × price per m³.
Worked example: 100 m² surface less 10 m² openings
- Net surface area is 90 m². At 12 mm total thickness, wet plaster volume is 1.08 m³.
- At dry factor 1.33 and 5% extra, dry ordering volume is 1.50822 m³.
- At 1:4 cement:sand and 1,440 kg/m³ loose cement density, cement is 434.37 kg, so buy 9 bags of 50 kg. Sand is 1.21 m³ (42.61 ft³).
Before you order
- Enter measured wall or ceiling surfaces, not the floor area of a house. Add separate faces and any reveals you intend to finish.
- Thickness and mix need approval for the substrate, exposure and finish. The accepted input range is not a recommendation for a single coat.
- This page estimates site-mixed cement-sand plaster. It does not estimate gypsum, lime plaster, proprietary premix, water, labour or curing supplies.
Reference: UltraTech masonry and plaster quality checklist. Starting values are editable examples; use the approved specification and supplier data.