Plaster Material Calculator

Cement and sand for the surface area you plan to plaster, with openings deducted.

Surface and plaster

Switching units converts the area and openings. Product coverage and prices keep their labelled units.

m²

Add the actual wall or ceiling faces to cover. Include both wall faces only when both will be finished; do not enter floor area.

m²

Total doors, windows and other excluded areas across the included faces. Add reveals separately to the gross area if needed.

mm

Enter the approved combined thickness. The calculator does not specify the number or thickness of individual coats.

Loose dry volumes: 4 means cement:sand = 1:4. Use your specified mix.

%

Material settings

Dry factor 1.33 and loose cement density 1,440 kg/m³ are estimating examples. Replace them with your site values; the allowance is applied separately.

kg/m³

Material prices (optional)

Leave a price blank until you have a supplier quote. Prices cover materials only.

Results

Cement bags to buy
9 bags
50 kg bags, rounded up. Sand remains an unrounded volume.
Sand volume
1.21 m³ (42.61 ft³)
Net plaster area
90.00 m²
Cement required
434.37 kg
Wet plaster volume
1.08 m³

Quantity breakdown

Dry volume including allowance
1.51 m³
Cement bought
450.00 kg
Estimated material cost
Awaiting supplier prices

Estimate only. Confirm quantities with your engineer or contractor. Read more

How it is calculated

  1. Net surface area = gross area - openings, converted to m². Each face must be counted explicitly.
  2. Wet plaster volume = net area × total thickness in mm ÷ 1,000. Dry ordering volume = wet volume × dry factor × (1 + allowance ÷ 100).
  3. For 1:s sand parts, cement mass = dry ordering volume ÷ (1 + s) × loose cement density. Bags = cement mass ÷ 50, rounded up. Sand = dry ordering volume × s ÷ (1 + s).
  4. Cost = full cement bags × price per bag + unrounded sand volume in m³ × price per m³.

Worked example: 100 m² surface less 10 m² openings

  1. Net surface area is 90 m². At 12 mm total thickness, wet plaster volume is 1.08 m³.
  2. At dry factor 1.33 and 5% extra, dry ordering volume is 1.50822 m³.
  3. At 1:4 cement:sand and 1,440 kg/m³ loose cement density, cement is 434.37 kg, so buy 9 bags of 50 kg. Sand is 1.21 m³ (42.61 ft³).

Before you order

  • Enter measured wall or ceiling surfaces, not the floor area of a house. Add separate faces and any reveals you intend to finish.
  • Thickness and mix need approval for the substrate, exposure and finish. The accepted input range is not a recommendation for a single coat.
  • This page estimates site-mixed cement-sand plaster. It does not estimate gypsum, lime plaster, proprietary premix, water, labour or curing supplies.

Reference: UltraTech masonry and plaster quality checklist. Starting values are editable examples; use the approved specification and supplier data.

Frequently asked questions

Do I enter wall area or floor area?
Enter the sum of the actual wall or ceiling faces to plaster. Floor area does not determine wall area. Count both wall faces only when both will be plastered.
How are openings handled?
Enter the combined area to exclude for doors, windows and other openings across the included faces. It cannot exceed the gross area. Include reveals in gross area separately if needed.
Does the calculator specify a plaster mix?
No. The 1:4 mix and 12 mm thickness are editable examples. Use the approved thickness and cement-sand ratio for your substrate, finish and exposure.
Why are dry factor and extra allowance separate?
The dry factor estimates loose dry ingredients from wet plaster volume. The extra allowance adds the entered percentage for site losses. Set both explicitly to avoid counting the same allowance twice.
How are materials rounded?
Cement is bought in full 50 kg bags rounded up from unrounded mass. Sand stays as an unrounded calculated volume for costing; the displayed volume has two decimal places. Confirm supplier ordering increments.
Can I use this for premixed or gypsum plaster?
No. This page splits loose dry volume into cement and sand. Proprietary premix and gypsum need their own product consumption data.
Esc