How the quantities are worked out
- Net wall area = length × height, minus each door and window (width × height × count).
- Brickwork volume = net area × wall thickness.
- Bricks = volume ÷ the volume of one brick with a 10 mm joint on each face, plus wastage, rounded up.
- Wet mortar = brickwork volume - the volume of the bricks themselves, plus 15% for frogs and uneven joints.
- Dry mortar = wet mortar × 1.33. Split it by the mix: in 1 : 6, cement is 1 part in 7.
- Cement: m³ × 1,440 kg ÷ 50 kg per bag, rounded up. Sand weighs about 1,600 kg per m³.
| Wall | Thickness | Mortar | Bricks per 100 sq ft | Used for |
|---|---|---|---|---|
| One brick | 9 in (230 mm) | 1 : 6 | about 900 to 1,000 | Outer and load-bearing walls |
| Half brick | 4.5 in (115 mm) | 1 : 4 | about 450 to 500 | Partitions and bathroom walls |
| One and a half brick | 13.5 in (345 mm) | 1 : 6 or 1 : 4 | about 1,350 to 1,450 | Retaining and basement walls |
| AAC block | 100 to 200 mm | Adhesive | about 80 to 85 blocks | Framed buildings, light walls |
Worked example: a 30 × 10 ft wall, 9 inches thick
- Gross area: 30 × 10 = 300 sq ft. One door of 3 × 7 ft and two windows of 4 × 4 ft take out 21 + 32 = 53 sq ft, leaving 247 sq ft.
- Volume: 247 sq ft × 0.75 ft = 185.25 cft (5.25 m³).
- Bricks: with 10 mm joints a clay brick takes up about 0.00225 m³, so the wall holds about 2,334 bricks, or 2,452 with 5% wastage.
- Mortar: 1.405 m³ wet, 1.869 m³ dry, giving 8 bags of cement and 56.58 cft of sand in 1 : 6.
Choosing bricks or blocks
| Red clay brick | Fly ash brick | AAC block | |
|---|---|---|---|
| Weight | 1,600 to 1,900 kg/m³ | 1,700 to 1,850 kg/m³ | 550 to 650 kg/m³ |
| Size | 228 × 108 × 70 mm (9 × 4¼ × 2¾ in) | 230 × 110 × 70 mm | 600 × 200 × 100 to 200 mm |
| Laid in | Cement mortar | Cement mortar | Thin-bed adhesive |
| Speed | Slow, many joints | Slow, many joints | Fast, few joints |
| Good for | Load-bearing walls | Load-bearing walls, even size | Framed buildings, heat insulation |
- Soak clay bricks in water for a few hours before laying so they do not pull water out of the mortar.
- Lay no more than about 1 m height a day so the lower courses can set.
- Cure brickwork for 7 days by keeping it wet.
Frequently asked questions
How many bricks are needed for 100 sq ft of 9 inch wall?
About 900 to 1,000 standard red clay bricks for every 100 sq ft of a 9 inch (230 mm) wall, including about 5% for cutting and breakage. Modular bricks need a few more because they are smaller.
How many bricks are needed for 100 sq ft of 4.5 inch wall?
About half as many as a 9 inch wall: roughly 450 to 500 bricks per 100 sq ft, with about 2 bags of cement and 10 to 11 cft of sand in 1 : 4 mortar.
Which mortar ratio should I use?
1 : 6 cement to sand is usual for 9 inch walls. Thin 4.5 inch partition walls need a richer 1 : 4 mix, because a single row of bricks relies more on the strength of each joint. Use 1 : 3 for parapets and work below ground.
Why multiply mortar by 1.33?
When water is mixed in, the fine cement fills the gaps between sand grains and the mix shrinks by about a quarter to a third. Multiplying the wet mortar volume by 1.33 gives the dry cement and sand to buy. The starting extra allowance for frogs and uneven joints is 15%. Both that allowance and the dry mortar factor are editable in Material settings.
How are door and window openings taken out?
Work out the gross wall area (length × height), then subtract the width × height of every door and window. The net wall area times the wall thickness gives the volume of brickwork.
How much cement and sand do 1,000 bricks need?
With 10 mm joints in 1 : 6 mortar, 1,000 clay bricks in a 9 inch wall take roughly 3 to 3.5 bags of cement and about 23 cft of sand. Richer mortar or fuller joints need more.
Are AAC blocks cheaper than bricks?
Per sq ft of wall they often cost about the same, but they are about 65% lighter, go up faster with far fewer joints, and need thin-bed adhesive (about 3.5 kg per m²) instead of sand-cement mortar. The lighter walls can also reduce the size of beams and columns.
Can I use my own material settings and prices?
Yes. Open Material settings to enter your product or site values, and Material prices to enter supplier quotes. The starting prices are examples, not current local rates. Price and coverage units stay as labelled when you switch length units. Custom wastage accepts 0 to 50%. Shared links retain your settings; Reset restores the examples.